Timeline 2

First page Back Continue Last page Overview Graphics

Timeline cont.

  • May 2004: LXCERT meeting (still no end date, “experiments need 1 month after full Application Area SW is available”, summer period worries)

  • June 2004: CEL3 -> SLC3, no real impact on certification

  • July 2004: LXCERT meeting (still no fixed end date, “end of September” target)

  • July 2004: LXPLUS test nodes available

  • Aug->October: POOL issue

    • Summer period: (some) production managers not available
  • Nov 1st 2004: SLC3 certified

  • Jan 17th 2005: LXPLUS migrated